• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2013 - Apr 2014
  • Estimated project cost $300,000
  • Australian Government contribution $150,000
  • State QLD

Project description

Current road has reached the end of its useful life and requires reconstruction and the intersection is being realigned for safety as there have been several near misses at this location.

Renew any expired drainage. Resheet and seal to a six metre bitumen seal standard (length 4.0km) as well as realign the intersection.

Total cost of proposed project is $300,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.