• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2013 - Dec 2013
  • Estimated project cost $873,090
  • Australian Government contribution $400,000
  • Local Council/Shire Ballarat City Council
  • State VIC

Project description

Collector road, one side industrial area the other side residential area. Road has failed because of heavy vehicles driving to industrial area.

Reconstruct damaged pavement, new drainage, kerb & channel and construct new service road on residential side.

Total cost of proposed project is $873,090

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.