• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2013 - Sep 2013
  • Estimated project cost $356,773
  • Australian Government contribution $256,339
  • Local Council/Shire Liverpool Plains Shire Council
  • State NSW

Project description

The road is badly deformed by wheel rutting with extensive areas of pavement failure and seal cracking.

The existing pavement will be excavated to a depth of 150mm, the existing sub-base and sub-grade will be chemically stablised to a thickness of 300mm then a new 150mm thick gravel base layer will be constructed and a 2 coat hot bitumen seal applied.

Total cost of proposed project is $356,773

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.