• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2014 - Jun 2014
  • Estimated project cost $163,800
  • Australian Government contribution $88,944
  • Local Council/Shire Local Government Association of the Northern Territory Inc
  • State NT

Project description

Washouts of road pavement on approaches to creek crossings at chainage 24.7 and scouring at creek crossings.

Rehabilitation of road pavement and construction of offlet drains and blocks. Construction of three cells box culverts 1200x1200x8m at creek crossing.

Total cost of proposed project is $163,800

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.