• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2014 - Jun 2014
  • Estimated project cost $334,000
  • Australian Government contribution $255,383
  • Local Council/Shire Rockhampton Regional Council
  • State QLD

Project description

Asphalt surface has cracked,potholed and has extensive pavement failures. Kerb and Channel has sunk and no longer on a grade that provides effective drainage.

Reconstruct kerb and channel both sides of street with seepage drains. Extend underground drainage system.Gravel resheet,cement stabilise and new asphalt seal existing pavement.

Total cost of proposed project is $334,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.