• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2013 - Jan 2014
  • Estimated project cost $95,700
  • Australian Government contribution $85,000
  • Local Council/Shire City of Albany
  • State WA

Project description

The seal on this road is stripping and cracking and the pavement on the north side of the road is failing

reconstruct the pavement in sections showing signs of failure and overlay with asphalt

Total cost of proposed project is $95,700

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.