• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2014 - Jun 2014
  • Estimated project cost $482,106
  • Australian Government contribution $82,805
  • Local Council/Shire Council of the City of Shellharbour
  • State NSW

Project description

This section of roadway has carried high traffic volumes since councils main sports field complex was constructed about 8 years ago, the road has cracked and fine material is leaching from the roadbase causing deformation of the pavement below.

Mill off the existing surface and replace with heavy duty asphalt (3620M2), also 28M2 of 150mm deep patching is required in front of the Fire Station.

Total cost of proposed project is $482,106

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.