• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Late 2014 - Early 2016
  • Estimated project cost $5,968,694
  • Australian Government contribution $4,774,955
  • Local Council/Shire Southern Midlands Council
  • State TAS
  • Corridor Hobart - Burnie

Project description

The project widened shoulders and installed wire rope barriers on the Midland Highway south of Kempton.

Benefits

The project achieved a 3 Star AusRAP Safety Rating on this section of the Midland Highway. The project improved safety, capacity and overtaking opportunities.

Funding

The cost of the project was $5,968,694. The Australian Government contributed $4,774,955 and the Tasmanian Government $1,193,739.

Timetable

Construction commenced on 12 December 2014 and was completed on 30 April 2016.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.