- Funding program Roads to Recovery Program
- Status Completed
- Transport mode Road
- Expected start/finish Jan 2015 - Jul 2015
- Estimated project cost $26,982
- Australian Government contribution $26,982
- Local Council/Shire Walgett Shire Council
- State NSW
Project description
Natural black soil surface that is badly rutted and corrugated and is un-trafficable during wet weather and hazardous for road users.Reconstruction and sealing work with 200mm thick gravel for approximately 100m in length with a width of 6m.
Project last updated:
Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.