• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2015 - Mar 2016
  • Estimated project cost $325,638
  • Australian Government contribution $325,638
  • State NSW

Project description

This section of road is suffering from bad pavement failures, cracking and drainage issues. A full reconstruction is to be be undertaken.

Existing pavement is to be rehabilitated and stabilized to an 8m formation width. Then a 150mm base layer of selected road base material and a 7m seal. Drainage work is to be carried out in conjunction with the above work.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.