• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2014 - Jan 2015
  • Estimated project cost $86,104
  • Australian Government contribution $86,104
  • Local Council/Shire Corporation of the City of Marion
  • State SA

Project description

There are a large number of cracks and also trench failures. This is a medium traffic road and classed as a Collector road in City of Marion’s hierarchy. It is also a bus route

Edge plane the asphalt 50mm, deep lift the pavement failures, then complete the project with a 50mm seal with modified AC – 2011 sq m

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.