• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2016 - Dec 2016
  • Estimated project cost $115,686
  • Australian Government contribution $115,686
  • Local Council/Shire Mornington Shire Council
  • State QLD

Project description

Stormwater flowing over the road for long periods during the wet season, makes access dangerous. The water washes away the existing gravel which has to be replaced.

Replace undersigned culvert with new culverts , 3 sets of 1200 x 450 mm x 9.6 m long culverts

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.