• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2014 - Nov 2014
  • Estimated project cost $24,900
  • Australian Government contribution $24,900
  • Local Council/Shire Gilgandra Council
  • State NSW

Project description

Road is primarily constructed from a sandy loam material being the natural surface. Surface has problems with longitudinal and lateral rutting and during wet periods this becomes a safety issue.

Reshape road and gravel sheet – Win and cart gravel – Spread gravel at 6m wide X 130mm thick, compacted to 100mm.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.