• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mid 2016 - Late 2018
  • Estimated project cost $228,368,000
  • Australian Government contribution $182,694,000
  • Local Council/Shire Hume City Council,Moonee Valley City Council,Moreland City Council
  • State VIC
  • Corridor Melbourne Urban

Project description

This project is Section 1 of the overall CityLink Tulla Widening Project.  Section 1 involved the widening and upgrading of the Tullamarine Freeway between the Melbourne Airport and Melrose Drive.  Specifically, Section 1 has:

  • provided an additional lane in each direction between the airport and Melrose Drive;
  • provided a grade separated south bound lane between Mickleham Road and the M80 Ring Road to address traffic flow issues caused by weaving movements;
  • implemented a managed motorways system including ramp metering and lane use management; and
  • provided ramp metering including priority queue bypass for buses on the inbound ramp from the Airport.

Benefits

The project will reduce travel times and improve safety. The overall CityLink Tulla Widening Project will reduce congestion by increasing capacity on the corridor by up to 30 per cent.

Funding

The Australian Government contributed $182.7 million towards this $228.4 million project.

Timetable

Construction commenced on 28 May 2016 and all lanes were open, ahead of schedule, on 21 September 2018.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.