• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2014 - Apr 2016
  • Estimated project cost $301,842
  • Australian Government contribution $301,842
  • Local Council/Shire Shire of Murray
  • State WA

Project description

The current road seal is 3.7m with significant pavement and edge failures, an ongoing reconstruction is being undertaken to increase the road standard and upgrade access from the Coolup area toward the west and ultimately link the new Forrest Highway.

To reconstruct and widen Fishermans Road with associated drainage (length - 1.4km) to a minimum road width of 6.5m with 1.2m shoulders.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.