• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2015 - Aug 2015
  • Estimated project cost $1,118,987
  • Australian Government contribution $696,996
  • Local Council/Shire Sunshine Coast Regional Council
  • State QLD

Project description

The proposed section of road has the following defects: - Crocodile Cracking; - Asphalt oxidisation; - Major Pavement repairs; - Potholes / pothole repairs; - Isolated Depressions; and - Crossfall / driveway issues.

Pavement Reconstruction - Full depth asphalt pavement. - Subsoil drainage replacement; - Profile out 255-355mm existing surface; and - Place 255mm asphalt.

Total cost of proposed project is $1,118,987

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.