• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2014 - Oct 2014
  • Estimated project cost $387,706
  • Australian Government contribution $300,000
  • Local Council/Shire Sunshine Coast Regional Council
  • State QLD

Project description

The proposed section has the following defects: - Extensive crocodile cracking; - Minor pavement failures; and - Minor potholing.

Asphalt resurfacing - 50mm Mill and Fill. - Profile out 50mm of existing surface; - Place waterproofing C170 bitumen seal; and - Place 50mm DG14 asphalt.

Total cost of proposed project is $387,706

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.