• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2015 - Sep 2015
  • Estimated project cost $408,270
  • Australian Government contribution $330,000
  • Local Council/Shire Alice Springs Town Council
  • State NT

Project description

Bitumen surface is cracked and failed due to poor drainage

Propose to reconstruct road for a length of 700M. works include removal of existing seal and base and rebuild road with new seal including improving the road drainage

Total cost of proposed project is $408,270

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.