• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2014 - Mar 2015
  • Estimated project cost $178,400
  • Australian Government contribution $148,156
  • Local Council/Shire Blayney Shire Council
  • State NSW

Project description

Aged seal allowing ingress of water, leading to failures

Patching works and reseal of entire length

Total cost of proposed project is $178,400

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.