• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2016 - Mar 2016
  • Estimated project cost $42,982
  • Australian Government contribution $42,982
  • Local Council/Shire City of Belmont
  • State WA

Project description

Excessive cracking of existing wearing course allowing egress of stormwater runoff into the base course causing pumping of fines to the surface damaging the road structurally.

Length, width and area of the job: 295m x 7.4m = 2,183m2. Profiling of the kerb edges of the asphalt wearing course. Retention of the existing kerbing both sides of the road and adjusting of existing drainage structures to match new road levels.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.