• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2015 - Aug 2015
  • Estimated project cost $90,000
  • Australian Government contribution $65,139
  • Local Council/Shire Sutherland Shire Council
  • State NSW

Project description

Narrow travelling lanes and poor sight distance on bends,narrow shoulder and no provision for pedestrians. section of road is subject to flooding due its elevation.Road widening at bends is required to improve safety.

It is proposed to raise and widen existing north bound carriageway(pavement area 870sqm). Road widening work include: raising subgrade level using road profiling material,120mm thick asphalt concrete basecourse and 50mm skid resistant wearing course.

Total cost of proposed project is $90,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.