• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2015 - Dec 2015
  • Estimated project cost $100,000
  • Australian Government contribution $100,000
  • Local Council/Shire Shire of Nannup
  • State WA

Project description

Centenary Drive has a historic drainage problem causing bitumen surface problems

Reconstruct and install drainage and kerbing to the intersection and adjoin approaches.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.