• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2015 - Jun 2015
  • Estimated project cost $40,222
  • Australian Government contribution $12,237
  • Local Council/Shire Inverell Shire Council
  • State NSW

Project description

The existing drainage in the area has reached the end of its useful life and requires replacement.

It is proposed to remove silt from existing table drains and construct new drainage structures under the road.

Total cost of proposed project is $40,222

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.