• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2015 - Mar 2016
  • Estimated project cost $434,000
  • Australian Government contribution $330,000
  • Local Council/Shire Ballina Shire Council
  • State NSW

Project description

Old pavement and seal has failed showing pavement rutting and shoving with significant patching, which requires high maintenance resources.

Reconstruction of pavement and seal for a length of approximately 200 metres with a variable width of 11 to 17 metres including removal and replacement of unsuitable subgrade and installation of kerbing for delineation of parking and tree areas.

Total cost of proposed project is $434,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.