• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2015 - May 2016
  • Estimated project cost $465,239
  • Australian Government contribution $465,239
  • Local Council/Shire Fairfield City Council
  • State NSW

Project description

The road is affected by numerous failures of road base, depressions and various types of cracks.

The proposed work includes the rehabilitation of road base by cement stabilisation, placement of spray seal and resurfacing with hot mix asphalt. Length =900m, Width =11.9m, Area =10710 m2.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.