• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2015 - Jun 2016
  • Estimated project cost $464,531
  • Australian Government contribution $464,531
  • Local Council/Shire Huon Valley Council
  • State TAS

Project description

The existing road is deficient in strength and is breakup in sections.

Replace existing drainage and culverts. Milling and stabilisation to a depth of 200mm, 120mm thick layer of compacted finely crushed rock and finish with a two coat seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.