• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2016 - Oct 2016
  • Estimated project cost $194,140
  • Australian Government contribution $194,140
  • State NT

Project description

Damaged road section with dust and dirt during dry season and muddy during wet season.

Drainage Earthworks Northen Drainway (Depth of cut 150mm) Loading Ramp Earthworks Fill from Loading Ramp to Roadway Access with Gravel. Shape, Compact and Trim Widen existing concrete slab by 4.7m at front and 1.3m each side

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.