• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2016 - Apr 2017
  • Estimated project cost $285,475
  • Australian Government contribution $285,475
  • State WA

Project description

Old seal is cracking allowing penetration of water into asphalt. Identified on councils road condition assessment as requiring intervention.

Profile out 60mm thick, install 25mm thick 7mm stone SMA corrector course, final wearing course to be 35mm thick 10mm stone SMA, link new drainage into existing system on Littlemore Road.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.