• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2016 - Jun 2016
  • Estimated project cost $95,625
  • Australian Government contribution $95,625
  • Local Council/Shire Sutherland Shire Council
  • State NSW

Project description

Significant ruts in the road pavement and the pavement roughness and surface texture have exceeded the acceptable standards. Resurfacing is required.

Full width (7.5m) road pavement resurfacing for 580m length. Works include mill and fill of pavement surface with 40mm thick asphalt concrete.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.