• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2018 - Nov 2018
  • Estimated project cost $177,675
  • Australian Government contribution $177,675
  • State NT

Project description

Seal pavement failure causing potholes and crocodile cracking and break up of pavement

Rip and seal Atnyer St from Irrpeng St centreline to Awerr Awerr Rd by applying 2 primer seal 14mm and 7mm pre-coated rock; top up 150mm of road base stabilized with 2% cement; installation of speed humps and road safety signage

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.