• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2016 - Jul 2016
  • Estimated project cost $41,204
  • Australian Government contribution $41,204
  • Local Council/Shire Kiama Municipal Council
  • State NSW

Project description

Existing wearing surface is cracked and potholed. Some heavy patching of pavement required.

Replace existing wearing surface with 30mm of new asphalt. Undertake deep lift heavy patching of pavement where required.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.