• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2017 - Oct 2017
  • Estimated project cost $120,374
  • Australian Government contribution $100,374
  • Local Council/Shire Shire of Morawa
  • State WA

Project description

Reconstruction of Intersection - Camber of Intersection to be lowered to alleviate drainage runoff from road into private property.

Reconstruct intersection to alleviate drainage problem then seal with a two coat seal and curb the both sides of the intersection Manning Road 0.52km to 0.54km Neagle Street 0.17 km to 0.19 km

Total cost of proposed project is $120,374

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.