• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2017 - Jul 2017
  • Estimated project cost $832,098
  • Australian Government contribution $253,728
  • Local Council/Shire Port Stephens Council
  • State NSW

Project description

Road pavement heavily potholed, narrow, cracking and deforming.

Widen and rehabilitate the existing pavement from Lisadell Road north 800m towards Ferodale Road.

Total cost of proposed project is $832,098

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.