• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2016 - Mar 2017
  • Estimated project cost $229,735
  • Australian Government contribution $222,117
  • State NSW

Project description

Existing old road pavement has an unacceptable ride quality due to utilities, potholes, pavement failures and delamination of wearing course.

Mill & fill. Remove approximately 50mm depth of existing sealed pavement over a length of 450 metres x 10 metres and then resurface with new asphalt and level correction.

Total cost of proposed project is $229,735

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.