• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2016 - Apr 2018
  • Estimated project cost $950,000
  • Australian Government contribution $850,000
  • Local Council/Shire Eurobodalla Shire Council
  • State NSW

Project description

Reconstruction of timber bridge which is currently in very poor condition. Structure has failed and can no longer support weight. Piers are rotted. Load limit reduced from 15 tonnes to 5 tonnes in November 2015 as structure is highly unstable.Stage 2 is replacement of the timber bridge

Removal of existing bridge and replace with new timber structure.

Total cost of proposed project is $950,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.