Project description

Intersection has insufficient capacity to manage traffic during detours associated with 2018 Commonwealth Games.

Upgrade intersection from roundabout to traffic signals. Construct shared path on Margaret Avenue between Gold Coast Highway and Old Burleigh Road. Construct shared path on Surf Parade between Elizabeth Avenue and Alexandra Avenue.

Total cost of proposed project is $2,113,377

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.