• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2016 - Dec 2016
  • Estimated project cost $39,930
  • Australian Government contribution $39,930
  • State NSW

Project description

Existing gravel surface has lost its original shape and hold water when wet. Large potholes have developed and constant maintenance requires. The section of the road has poor drainage on the south side of the road fronting the properties.

Rework existing gravel pavement lay and compact 100mm layer of DGB20 pavement material. Table drain is to be regarded and replace existing drainage pipes with 300mm and 375mm pipes. Spray 10mm primer seal. Line marking and erection of roadside furniture.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.