• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2017 - Apr 2017
  • Estimated project cost $109,705
  • Australian Government contribution $109,705
  • Local Council/Shire Walcha Council
  • State NSW

Project description

Existing road is very deteriorated, it is Council's top priority within the township.The road has extensive pothole pathcing that has lead to a very rough surface.

Widening the existing pavement and seal.Continue with drainage upgrades addressing poor drainage throughout the site.Drainage upgrades will include new kerb and gutter along the southern side of the road.Works will begin at 0.000km and will end at 0.500 km

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.