• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2017 - Apr 2017
  • Estimated project cost $72,289
  • Australian Government contribution $72,289
  • Local Council/Shire Walcha Council
  • State NSW

Project description

Deterioration of the road due to soft underlying pavement

Heavy patching work a 280 m long x 6 m wide section with 200 m thick gravel, C170 bitumen binder, 10 mm and 7 mm precoated aggregates

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.