• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2017 - Sep 2017
  • Estimated project cost $103,359
  • Australian Government contribution $103,359
  • Local Council/Shire City of Belmont
  • State WA

Project description

Existing red asphalt wearing course has come to the end of its useful life with cracking showing through, minor deformation of road and kerb damage along East side of the road.

Length, width and area of job: 124m x 11.5m = 1,426m2. Profile out existing red asphalt over the full width of the road, replace kerbing along the East side of the road and overlay full extent of the job with a new wearing course.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.