• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2016 - Feb 2017
  • Estimated project cost $196,607
  • Australian Government contribution $196,607
  • Local Council/Shire Shire of Boddington
  • State WA

Project description

Rejuvenation required ie. the existing pavement is cracked and ageing and nearing the end of its useful life and a new seal needs to be applied to protect and rejuvenate the current seal to preserve the asset.

Crack sealing then 10/7mm polymer modified bitumen reseal for straight line chainage 0 to 350 metres and from straight line chainage 500 metres to straight line chainage 3150 metres plus 150 metres of micro surfacing from straight line chainage 350 metres to straight line chainage 500 metres.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.