• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2018 - Nov 2018
  • Estimated project cost $1,800,000
  • Australian Government contribution $986,160
  • State NT

Project description

Gravel road pavement causing dust to enter domestic dwellings increasing risk to residents. Road is subject to flooding during the wet preventing access to airport and waste facility.

Reconstruction and lift of pavement and seal to a width of 6 meters. Construction of four concrete causeways with associated drainage. Installation of road signs to improve road safety.

Total cost of proposed project is $1,800,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.