• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2016 - Aug 2016
  • Estimated project cost $66,129
  • Australian Government contribution $66,129
  • Local Council/Shire City of Port Phillip
  • State VIC

Project description

Deformed asphalt surface has been identified through road inspections. The pavement surface has changed from originally constructed profile which may directly influence the riding quality, water ponding and skid resistance. Asphalt resheeting improves pavement performance with regard to the strength and riding quality.

40mm thick asphalt overlay covers the existing surface of 221m length and 6.3m width (area of 1400m2)

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.