• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2017 - Jun 2017
  • Estimated project cost $62,932
  • Australian Government contribution $62,932
  • Local Council/Shire Shire of Bruce Rock
  • State WA

Project description

There is little to no gravel left on the road. There are rocks in some areas which are becoming a problem, and clay rising to the top in some areas of the road which is causing the road to be slippery. Sections of road may pose a danger to road users, particularly after rain.

Clear the shoulders of weeds and overhanging trees, then regravel for four kilometres out to 10 metres width. Reinstate the table drains floodways.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.