• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2017 - Jun 2017
  • Estimated project cost $325,521
  • Australian Government contribution $300,000
  • State NSW

Project description

The road surface is affected by numerous crocodile cracks, pavement failures and potholes indicating that the road has structural deficiencies. It has been patched multiple times in the past. It is a bus route.

The proposed works includes replacement of road base with asphalt and resurfacing with asphalt. Length = 220 m; Width = 12 m; Area = 2640 m2.

Total cost of proposed project is $325,521

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.