• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2017 - Apr 2017
  • Estimated project cost $155,586
  • Australian Government contribution $150,000
  • State NSW

Project description

Failed road pavement associated to pavement reaching the end of its useful life. Pavement shows large signs of block, crocodile, longitudinal, transverse cracking also pavement failures, ravelling, stripping, flushing and failed kerb and guttering.

Pavement rehabilitation/stabilisation, spray sealed bitumen wearing surface.

Total cost of proposed project is $155,586

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.