• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2017 - Jun 2017
  • Estimated project cost $131,500
  • Australian Government contribution $131,500
  • Local Council/Shire Shire of Mt Marshall
  • State WA

Project description

Existing bitumen surface condition is aged with extensive cracking. A reseal is required to preserve the pavement.

Reseal 4.400 metres at 7.0 metres wide with a 14 millimetre cutback seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.