• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2017 - Jun 2017
  • Estimated project cost $1,815,528
  • Australian Government contribution $1,500,000
  • Local Council/Shire Fraser Coast Regional Council
  • State QLD

Project description

The existing road has insufficient pavement depth, is narrow, has poor vertical geometry and is subject to inundation that comprises safety.

The project provides for full reconstruction of approximately 2050m of pavement; works will include: services relocations, bulk earthworks, major culverts, kerb and channel installation, sub soil drainage, pavement works, bitumen surfacing, line marking and signage.

Total cost of proposed project is $1,815,528

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.