• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2017 - Sep 2018
  • Estimated project cost $3,154,421
  • Australian Government contribution $1,383,634
  • Local Council/Shire Coffs Harbour City Council
  • State NSW

Project description

Pavement is in poor condition, it's narrow and poor drainage so is dangerous with no formalised shared pathway.

Upgrade including kerb and gutter, stormwater drainage. Box out unsuitable base and subgrade and replace with 400mm of Aus Spec quality base material. Seal with 10mm spray seal then overlay with 40mm AC14 asphalt. Line mark. 185m long. One lane each way. Also included a 2.5m wide shared path full length.

Total cost of proposed project is $3,154,421

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.