• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2018 - Mar 2019
  • Estimated project cost $178,000
  • Australian Government contribution $113,000
  • Local Council/Shire Central Goldfields Shire Council
  • State VIC

Project description

Drive In Court, 371 metres long is an Urban Industrial Access road where the existing asphalted road pavement, which is 9 metres wide between kerbs has failed. The road surface is cracked and the pavement has rutted and heaved and has deteriorated.

The existing pavement is to be stabilised and strengthened to 200mm deep and 9 metres wide, totalling 3,339 square metres and resurfaced with a 40mm deep heavy duty asphalt.

Total cost of proposed project is $178,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.